Deepening of the navigation channel in the Port of Koper
The deepened port channel will enable access to larger cargo ships with more containers.
The investment included deepening of the navigable channel of basin 1 at the cargo port of Koper to the depth of -15 meters. In the framework of the project, a cassette was built in the Ankaran Bonifika area, in which about 150,000 m3 of marine mud was deposited as a result of the deepening of the channel.
Most cargo ships that arrive at the port of Koper have a draught of 13.5 meters at full load.
Type of project:Deepening of the navigation channel
Client:
Luka Koper d.d.
Status:Completed